LEBUHRAYA DUKE FASA 3 SDN BHD - 2018 |
||||||||
Report ID | 5823 | Popularity | 1639 views 197 downloads | |||||
Report Date | Nov 2018 | Product | ||||||
Company / Issuer | Lebuhraya Duke Fasa 3 Sdn Bhd | Sector | Infrastructure & Utilities - Toll Road | |||||
Price (RM) |
|
|||||||
Rationale |
MARC has affirmed its
rating of AA-IS on toll
concessionaire Lebuhraya DUKE Fasa 3 Sdn Bhd’s (DUKE 3) RM3.64 billion Sukuk
Wakalah with a negative outlook. Wholly owned by Ekovest Berhad, DUKE 3 is
undertaking the design, construction, financing, operations and maintenance
of Setiawangsa-Pantai Expressway (SPE), a 32-km elevated dual two-lane
carriageway. The toll road project is being built under a concession agreement
with the Government of Malaysia ending August 5, 2069. The negative outlook
reflects the rating agency’s concerns over the continued regulatory
uncertainties on the direction of the toll industry. In this regard, matured
toll concessionaires which are able to generate sufficient cash flows and
maintain healthy cash balance levels to meet financial obligations without
substantial reliance on government compensation would be in a better position
to weather any regulatory adjustments. The affirmed rating is
underpinned by the sufficient construction progress and adequately structured
sukuk repayment profile that accommodates the ramp-up of traffic on the
expressway. As at September 30, 2018, SPE’s actual overall progress remains
steady, standing at 42.40% against the planned progress of 42.35%, according to
the independent consulting engineer (ICE). The rating agency also notes that
any cost arising from delays would be passed to the engineering, procurement
and construction (EPC) contractor through the back-to-back liquidated
ascertained damages (LAD) arrangement of RM10,000 per day of delay under the
fixed-sum contract. An irrevocable and unconditional bank guarantee of RM184.5
million (5% of EPC costs) further mitigates the construction cost
overruns. As at October 31, 2018,
DUKE 3 has incurred RM1.46 billion on the project while total designated
account balances stood at RM2.74 billion. In respect of land required for
construction of the expressway, as at September 30, 2018, DUKE 3 has utilised
RM210.6 million for land acquisition purposes. As sizeable government funding
of up to RM350 million has been set aside for land purchases, financial risk
associated with land acquisition has been minimised. DUKE 3 expects to commence
work on the remaining lots once they have taken formal possession by end-2018.
MARC understands that DUKE 3 is waiting for the disbursement of the reimbursable
interest assistance (RIA) amounting to RM460 million from the government. As at
October 2018, DUKE 3 has only received its first payment of RM100 million from
the government in July 2017. Under the latest base case
cash projections, DUKE 3’s projected minimum and average pre-distribution
finance service cover ratios (FSCR) with cash balance stand at 2.24 times and
2.61 times during the sukuk tenure. The revised projections assume the
disbursement of the remaining RIA of RM460 million in 1H2020, GST savings of
RM56.2 million from the construction costs and higher interest income of RM88.5
million, among others. The sensitivity analysis indicates that the project cash
flow can withstand up to a 13% construction cost overrun or 12 months’ delay in
the commencement of tolling operations before breaching the FSCR covenant of
1.50 times in 2023 and 2026. It also reveals that DUKE 3 is vulnerable to a
breach in the equity-to-capital ratio of 16% by 2023. The projections also show
that in the event the initial traffic growth is around 23% during the ramp-up
period (2020-2024), the traffic growth rate would subsequently have to register
6.5% per annum against 3.6% of operating expense growth to break even.
Correspondingly, if the highway meets its projected initial traffic growth of
26% during the ramp-up period, DUKE 3 would break even with a traffic growth
rate of 4.7% during the post ramp-up period (2025-2039). Major Rating Factors Strengths
Challenges/Risks
|
|||||||
Related |