LEBUHRAYA DUKE FASA 3 SDN BHD - 2019 |
||||||||
Report ID | 6042 | Popularity | 2067 views 164 downloads | |||||
Report Date | Nov 2019 | Product | ||||||
Company / Issuer | Lebuhraya Duke Fasa 3 Sdn Bhd | Sector | Infrastructure & Utilities - Toll Road | |||||
Price (RM) |
|
|||||||
Rationale |
MARC has affirmed its rating of AA-IS on toll concessionaire
Lebuhraya DUKE Fasa 3 Sdn Bhd’s (DUKE 3) RM3.64 billion Sukuk Wakalah. The
rating outlook remains negative. DUKE 3, a wholly-owned subsidiary of Ekovest Berhad
(Ekovest), is undertaking the design, construction, financing, operations and
maintenance of the 32.1-km Setiawangsa-Pantai Expressway (SPE) in Kuala Lumpur.
SPE will connect Middle Ring Road 2 at Wangsa Maju to Kerinchi Link adjoining
Federal Highway and is being built under a concession agreement (CA) with the
Malaysian government ending August 5, 2069. The Sukuk Wakalah was put on a negative outlook last year
over the uncertainty on the direction of the toll road sector following the
government’s decision to review toll road concessions and their tariff
framework. The negative outlook also incorporated a delay in receipt of the
reimbursable interest assistance (RIA) from the government amounting to RM460.0
million that could potentially affect DUKE 3’s debt-servicing ability.
While the sector’s regulatory environment appears more
settled and the RIA has been fully received in April 2019, the rating outlook
remains negative as there is now a risk of time overrun. This is arising from
the change in alignment at the Bandar Malaysia stretch, a circumstance that is
beyond the scope of DUKE 3’s control. While the issue is now resolved, that
change in decision over the road alignment at Bandar Malaysia, and the
consequent need to restart the land acquisition process have set the
construction back by 14 months. As a result, project completion is now
projected to be in November 2020 instead of February 2020 as initially planned.
Under the latest work plan, progress of construction as at end-September 2019
stood at 62.8% against the scheduled 64.7%, slightly behind schedule but deemed
manageable. Commencement of tolling operations is accordingly expected
to be deferred to January 2021, nine months later than the initially scheduled
April 2020. This could compromise DUKE 3’s debt protection metrics. However, a
Construction Reserve Account (CRA) is in place to mitigate potential cash flow
issues arising from tolling delays and cost overruns. In this regard, Ekovest
had procured a Bank Guarantee (BG) from AmBank Islamic amounting to RM184.5
million to meet the requirement under the Minimum CRA Balance (i.e. 5% of the
construction cost). The sum under the BG can be drawn down partly and when
required to maintain the cash buffer at a level that meets the covenanted
finance service cover ratio (FSCR) of 1.50 SPE is expected to be completed within the RM3.86 billion
budgeted cost. In the event of any cost overruns, this is expected to be
absorbed by Ekovest given the fixed-price contract entered into with the
engineering, procurement and construction (EPC) contractor. Meanwhile, project
funding is sufficient to finance completion; as at end-September 2019, DUKE 3
had close to RM2 billion in the Investment Funds (i.e. unutilised funds drawn
down from the facility which were invested in money market instruments) to fund
the remaining 37% of works. In addition, there is approximately RM238 million
in the Designated Accounts to help meet the next semi-annual profit payment of
RM109.3 million due in February 2020. Under the latest cash flow projections that take into
consideration the CRA, DUKE 3’s minimum and average pre-distribution FSCR with
cash balance are projected at 2.36x and 2.68x. With MARC’s sensitivity of a
six-month tolling delay (i.e. start of tolling in July 2021 versus base case’s
January 2021), our projections indicate that DUKE 3 can still maintain its
minimum FSCR around 2.1x. Our sensitivities indicate that DUKE 3’s cash flow
can tolerate up to approximately 10% reduction in traffic volume coupled with
the six-month tolling delay before it breaches the 1.50x covenanted FSCR in
2035. MARC will continue to monitor the project progress closely.
The rating could be downgraded if the project is unlikely to be completed
within the current timeline (i.e. November 2020) and cost parameters.
Conversely, evidence that the project is likely to be completed on time and
within cost could stabilise the rating outlook. Major Rating Factors Strengths
Challenges/Risks
|
|||||||
Related |